现在的位置: 首页 > 综合 > 正文

Time Management – Schedule Development Process

2013年08月02日 ⁄ 综合 ⁄ 共 1201字 ⁄ 字号 评论关闭
Schedule Development Process

It is the core of time management.

it's the process where you put it all together.

input: Resource Calendar/Network Diagram/Activity List/Activity Attributes/Activity Duration Estimates /Activity Resource Requirements/Project Management Plan/Organizational Process Assets/ Scope Statement

output: schedule development

The Critial Path is the longest duration of activities list(from start to end)

About Activity node(apart from duration), also includes:

ES(Early Start): the early start of the first activity in a path is one. the early start of an activity is the early finish of the previous activity plus one

EF(Early Finish): the early finish of an activity is its ES plus its duration minus one

LS(late start):

start with the critical path and take a backward pass through the path.

move backwards through the path, filling in the LS by subtracting the duration from the LF and add one.

LF(late finish): start by filling in the LF of the last activity in each path which is the same as the EF of the last activity in the crital path. the LF for each activity is the LS of the next one on the paht minus one.

tools&techniques:

a. Monte Carlo Analysis

b. Schedule Model(PM software )

c. critical chain method( resource dependencies)

d. resource leveling

e. applying calendarsf. adjusting leads and lags

output:a. scheduleb. milestone listc. schedule baselined. updates and requested changes

抱歉!评论已关闭.